September's Progress


Work to the High Street Public Realm Project started at the beginning of September.
In the first six weeks a 4-way traffic lights system was introduced to begin the temporary road widening. Trees, which are affected by the new layout, have been removed. In particular the trees outside the Town Hall and the Muggleton Inn pub. New planting is scheduled for next year.

On September 19 a full road closure was put in place at Lower High Street to remove existing planters and to put down a new permanent footpath. Work has also begun on the junction of High Street and Pudding Lane.

Eurovia has reported that good progress has been made through September and they are currently ahead of schedule.

October

At the beginning of October the footpaths at the bottom end of Middle Row started to be widened; the roads were starting to be dug up and new kerbs put in and new drainage channels were established. 

On October 15 the Lower High Street Road closure was lifted.

For the remainder of October the granite paving will be laid to the bottom of Middle Row, although Eurovia is still awaiting further information from Statutory Authorities about modification works required to the existing drainage in the carriageway. More information on this will follow next month.

On Monday, October 17 the traffic will be reverted back to a 4-way traffic light system and traffic will be diverted to the Royal Star Arcade side of the High Street at the new point where traffic will go down to one lane. This will allow the other side of the road to be completed.

Footpaths from the bottom of Middle Row to Mill Street will continue to be dug up. Pedestrians must use Bank Street as an alternative route.

November

As granite paving on the Town Hall side of Middle Row nears completion, Phase 2 will begin from Pudding Lane. Southern Water will also be completing existing drain repairs at the end of phase 2 opposite the Town Hall.

High Street Progress

High Street Progress

High Street Progress

December

Completion of the Pudding Lane Junction including  the new throttle Point (courtesy crossing).

Northern (Royal Star side) footpath works to continue towards Week Street.

Construction of the second throttle point (courtesy crossing) in front of the British Heart foundation Clothing Shop to begin.

The site will close on December 22 for two weeks. All areas will be cleared as much as possible and made safe where necessary.