Launch of the Open Design Competition January 2009
Public Exhibition of all the submissions at the Town Hall April 2009
Winning Team selected: Letts Wheeler Architects May 2009
Design development and stakeholder consultations May-December 2009
Public Consultation, held at The Mall in Maidstone January 2010
Planning Permission granted July 2010
Exhibition at the Kent County Show July 2010
Contracts signed on June 9, 2011
Work to start on site September 5, 2011. Work will take 32 weeks with a two week break over the Christmas period